Contract Costing
Basic Terms In Contract Business
- Contract Price
- Value of Work Certified
- Degree of Completion
- Cost of Work Done
- Cost of Work Uncertified
- Notional Profit
- Actual Profit
- Cash Received / Progress Payment Received
- Retention Money
Formula
- DOC = WC/CP * 100
- Value of work Certified = CP X DOC
- Cost of Work Certified = Cost of work Done - Cost of Work Certified
- Cost of Work Uncertified = Cost of Work Done X % of Work uncertified % of Work Done
- % of Work Uncertified = % of Work Done - DOC
- Cash Received = Value of work Certified X % of Cash Received
- Notional Profit =Value of Work Certified - Cost of WUC - Cost of WD
- Retention money = Value of WC X % of Retention Money
OR
- Retention money = Value of WC X % of Retention Money
Cost of Work Done
Mat. Consumed at Site
(+) Wager
(+) Indirect Exp.
(+) Supervision Charges
(+) Depreciation of fixed Assets
(+) Sub-Contract Charges
(+) Other Misc. Expenses
Accounts Prepared In the books of Contractor
- Contract A/c
- Distribution of Notional Profit
- Balance Sheet
Distribution of Notional Profit
- Profit T/f To Costing P&L A/c
- Profit T/f To WIP Reserve A/c
Estimated Profit
Contract Price - Total Estimated Cost
#Total Estimated Cost = Cost of WD - Futher Cost
#Estimated Profit = CP - Total Estimated Cost
Definitions
- I Hope This Notes is Helpful in Your Study. Stay Connected with CMA Students Community for more notes. You can connect through different social media platforms. You Can also Give your Suggestion to us for better
- Keep Learning ! Keep Loving ! Keep Supporting Us.
- if you want PDF of this notes you can drop your message in the comment box.
.png)
0 Comments
Please Do Not Enter Any Spam Link In The Comment Box